You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Breakwater Pulau Pramuka Sudah 30 Persen
.
photo Rudi Hermawan - Beritajakarta.id

Pramuka Island Breakwater Project Has Touched 30 Percent

We have done this since July 5. And now it has touched 30 percent

The 426-meter long breakwater construction along the east coast of Pramuka Island, Panggang Island Urban Village, North Seribu Islands has reached 30 percent. It is expected to be completed by the end of this year.

Seribu Islands Water Resources Sub-dept. Head, Ahmad Saiful stated that it has been carried out since last July.

Breakwater Construction on East Side of Sebira Island is Completed

"We have done this since July 5. And now it has touched 30 percent," he stated, Monday (9/17).

To realize it, his side has spent Rp 13 billion.

"It is targeted to be finished on December 10, 2018," he said.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1207 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1052 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye905 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye730 personFolmer
  5. Jakarta Provincial Government Holds Christmas Carol

    access_time18-12-2024 remove_red_eye577 personDessy Suciati