Pembangunan Breakwater Pulau Pramuka Sudah 30 Persen

Pramuka Island Breakwater Project Has Touched 30 Percent

We have done this since July 5. And now it has touched 30 percent

The 426-meter long breakwater construction along the east coast of Pramuka Island, Panggang Island Urban Village, North Seribu Islands has reached 30 percent. It is expected to be completed by the end of this year.

Seribu Islands Water Resources Sub-dept. Head, Ahmad Saiful stated that it has been carried out since last July.

Breakwater Construction on East Side of Sebira Island is Completed

"We have done this since July 5. And now it has touched 30 percent," he stated, Monday (9/17).

To realize it, his side has spent Rp 13 billion.

"It is targeted to be finished on December 10, 2018," he said.

Linked News
Popular News indeks
  1. Posyandu-Posbindu Services Reach 1,600 Seniors and Toddlers in Utan Panjang

    access_time07-04-2026 remove_red_eye822 personFolmer
  2. West Jakarta BPN Holds Mobile Land Service in Kembangan

    access_time06-04-2026 remove_red_eye667 personBudhi Firmansyah Surapati
  3. Palmeriam Market Adopts QRIS Digital Payment System

    access_time08-04-2026 remove_red_eye666 personNurito
  4. Jakpro Promotes Integration Between JIS and KRL Station

    access_time10-04-2026 remove_red_eye580 personAldi Geri Lumban Tobing
  5. Residents Appreciate Drainage Revitalization on Jalan Manggis

    access_time10-04-2026 remove_red_eye547 personNurito